Construction Relocation Maps & Timeline

Timeline (updated 12/13... subject to change)


  • Aug-Dec 15 2022 – Cleaning, consolidation, and preparation to move Building H classrooms and offices

  • Dec 16, 2022 – Complete packing for move

  • Dec 19-22, 2022 – Moving company transports labeled items to new campus locations and/or long-term storage facility

  • Dec 23-Jan 3, 2022 – ECC main campus closed for winter break

  • Jan 4, 2023 – ECC main campus reopens following winter break

  • Jan 4-13, 2023 – Faculty and staff prepare classrooms and offices in new locations

  • Jan 17, 2023 - Spring semester begins

  • Nov-Dec 2023 - Pack classrooms and offices for return to Building H

  • Dec 21-Jan 1 – ECC main campus closed for winter break

  • Jan 2, 2024 – ECC main campus reopens following winter break

  • Jan 2-12, 2024 Building H classroom and lab setup

  • Jan 16, 2024 spring semester begins